Road Work

High Acres Road

Project Completed: October 22, 2015

Location: Randolph, NH
Owner: Town of Randolph

This Project involved Road Reconstruction to correct a deficient road bed.  Preexisting conditions had left the road barely passable and difficult to maintain.  Work included; replacing aging cross culverts, reshaping roadside swales, removing rocks and replacing unsuitable materials. The road surface was turned to a gravel surface in order to save costs.

This roadway had suffered from a poor subgrade with little in the way of gravel.  Rocks were protruding through the pavement […]

Middleton Road

Project Completed: September 30 2015

Location: Wolfeboro, NH
Owner: Town of Wolfeboro
Engineer: Underwood Engineer, Inc.

This Project was a Road Reconstruction to correct drainage and a deficient road bed.  The existing roadway was a NHDOT unnumbered road which was to be turned over to the Town upon completion.  The work included enhancements and repairs to the existing drainage systems and removal of unsuitable materials.  Road work went from Route 28 (Weston’s Corner) to New Durham Town line; Approximately 1.75 miles.

As this roadway […]

Oak Ridge Road Reconstruction

Project Completed: May 30, 2016

Location: Madison, NH
Owner: Village District of Eidelweiss
Engineer: Fluet Engineers

This Project was a Road Reconstruction to correct drainage and a deficient road bed.  The work included enhancements and repairs to the existing drainage systems, removal of unsuitable materials and relocating a waterline.  Road work went from the bottom of Oak Ridge Road up approximately 1,300 feet.

As this roadway had become severely deteriorated over the years it had become a problem as it could no longer be patched or repaired and […]

Frost Brook Bridge

Project completed May, 2014

Location: Madison, NH
Owner: Town of Madison, NH
Design Build Team: G. W. Brooks and French Engineering

The Project involved the removal of a failing Red Listed bridge (in this case twin 48″ Culverts) and installation of a new precast rigid frame bridge.  As a cost savings method and in order to expedite the project it was a put out to bid as a Design-Build bridge.  This project was funded through a capital reserve plan which removed a great deal of the […]

Sheridan Road Reconstruction

Project completed June, 2013

Location: Moultonborough, NH
Owner: Town of Moultonborough, NH
Engineer: KV Partners

Work on this Project consisted of reconstruction of deteriorating roadway through a narrow Right-of-Way within in a neighborhood that was sensitive to disruptions and construction nuisances. The work included installation of closed drainage systems to carry water existing surface drainage systems. Also included within the project the complete box reconstruction of the supporting gravel structures of the roadway to repair existing deficiencies. Work also narrowed the existing roadway […]

Route 4 and Morgan Way Intersection Improvements

Project completed April, 2012

Location: Durham, NH
Owner: Town of Durham and NH DOT
Engineer: CMA Engineers

The Project involved the addition of a turning lane on the East bound side of Route 4. In addition to the turning lane there was also work performed to improve drainage through the Project. The Project required the cutting of a very dense grove of trees that were intertwined with power lines running 19,900 Volts. In addition to the line clearing there was also a need to coordinate the […]

Maple Ridge Road Drainage & Reconsruction

Project Completed September, 2010

Location: Sandwich, NH
Owner: Town of Sandwich

This project was a road reconstruction project of a small rural road.  Reclaiming of the existing paved road helped to reduce costs over full reconstruction while still giving a good finished product better than just an overlay.  Additionally we removed the existing Reinforced Concrete cross culverts and replacement them with aluminized steel culverts.  State Spec. crushed gravel was installed over the reclaim prior to paving.  Ditching along the entire road was completed and installation of stone […]

Cedar Ridge Condos, Drainage and Parking Improvements

Project completed July, 2010

Location: Portsmouth, NH
Owner: Cedar Ridge Condominiums
Engineer: Ambit Engineering

With insufficient gravels under the existing pavement the parking lots and driveways had significant cracking and deformation. In addition to the pavement issues there was also a need to update the existing drainage system. With the update of the drainage system there was a need to rebuild some drainage structures and add poly inlet liners to extend the life of the structures. In addition to the repairs to the existing system, several […]

3/4 Mile Private Driveway, Silver Lake Home

Project completed March, 2010

Location: Madison, NH
Owner: Girouard Family
Construction Manager: Malcolm Thomas

This Project was a multi-phased project that centered around the construction of new private residence. All phases of the site work were awarded to G. W. Brooks and Son, Inc. The first phase involved the installation of an access road to the future home site. The existing woods road had trees grown very tight to it requiring clearing, in addition the existing road only went approximately halfway to the […]

Rice Hill Road Drainage and Road Reconstruction

Project completed September, 2009

Location: Freedom, NH
Owner: Town of Freedom, NH
Contracted By: Town of Freedom Highway Department

For this Project we were hired by the Town of Freedom to work alongside their crews in the reconstruction of Rice Hill Road. In the process of the reconstruction new under-drain was installed and new culvert crossings and head walls. The reconstruction required the removal of the poor performing existing gravels, installation of a woven roadway fabric, followed by the installation of new NH DOT spec. crushed […]