Site Work

Country Woodland Estates

Location: Freedom, NH
Owner: Wendell and Pauline Brooks

The Project involved the clearing and grubbing of two subdivisions. The roads were installed with all utilities installed underground. The roadways were installed to the Town of Freedom specifications with asphalt pavement for the driving surface. Each road is approximately 850 feet long with a cul-de-sac at the end of each.

The Project was started upon realizing that portions of the land adjacent to the G. W. Brooks and Son, Inc. yard, shop, and office land […]

Tamworth Family Medicine

Project completed April, 2007

Location: Tamworth, NH
Owner: Huggins Hospital
Engineer: White Mountain Survey Company, Inc.
General Contractor: Bauen Corporation

The Project involved the site work for a new family medicine facility. The Project entailed the overall grading of the site, excavation for the building, parking lot installation, and other associated site work tasks. A particularly unique feature of the project was a large drainage swale running down the north side of the project.

The Project is sited along the highly visible Route 16 corridor in Tamworth, NH […]

Tamworth Brett School Addition and Ballfield

Project completed 2004

Location: Tamworth, NH
Owner: Tamworth School District
Engineer: White Mountain Survey Company, Inc.
General Contractor: Bauen Corporation

The addition to the building was for additional classrooms and a new gymnasium. For the addition we performed the associated site work for the new foundation. Along with this we also installed drainage and select gravels for expanded driveway and parking lots. The ball field was reconstructed to improve the playing surface and provide for better turf establishment and drainage.

Carroll County Courthouse

Project completed 2003

Location: Ossipee, NH
Owner: Carroll County, NH
Engineer: White Mountain Survey Company, Inc.
General Contractor: Hutter Construction Corporation

The Project required the installation of a culvert to access the site as a permanent driveway. The overall Project called for a balancing cut and fill for the site where the site was leveled and on one end an eight foot fill was required. The building excavation was then able to commence and utilities to the new building were soon installed below ground. Once the overall […]

Effingham Elementary School

Project completed 2003

Location: Effingham, NH
Owner: Govenor Wentworth School District
Engineer:White Mountain Survey Company, Inc.
General Contractor: Bauen Corporation

The Project was to complete all associated site work for a new 29,000 square foot elementary school. The work included the clearing of the lot, grubbing of all stumps, regrading of the lot, excavation for the building, and construction of sidewalks, driveways, septic system, athletic field, and playground area.