Project completed 2014
Location: Portsmouth, NH
Owner: Carroll County, NH
Engineer: Tighe & Bond
Project Description
Project Background
The existing parking lot was a mixture of gravel and paved portions. With the ongoing improvements to the course the parking lot was a logical improvement. The project required the course to stay open throughout and phasing of the work to make this possible. Cooperation of all parties allowed this project to become a great improvement for a stellar golf course.
Project Goals
Issue: The facility needed to stay open throughout the construction.
Solution: Through cooperation with the Pease Golf Course we were able to phase the project and keep access to the facilities.
Issue: The new parking lot was a large increase in the paved surfaces on site
Solution: The new parking lot utilized porous pavement within the parking stalls on a large portion of the new layout.