Project completed May, 2012
Location: Alton, NH
Owner: Town of Alton, NH
Engineer: Dubois and King
Project Description
Project Background
Project Goals
Solution: With the new precast arch structure there is no need for weight posting any longer.
Issue: Potential that the existing bridge would be a choke point along the brook and result in bridge or roadway failure
Solution: The new bridge using a natural stone bottom and enlarged interior dimensions should provide for a safe buffer in the event of extreme water flows.
Issue: A historic dam is adjacent to the bridge site which must not be disturbed.
Solution: The crews worked diligently to limit work near the dam and in the end there was no disturbance made to the dam.
Issue: Aesthetics were extremely important to the abutters.
Solution: The new precast bridge has a synthesized ashlar stone finish to help it to blend with the rural environment.
- Existing Bridge prior to removal
- Up Stream side of the existing bridge
- Water diversion installed, bridge deck removal underway
- Setting up for precast footing installation
- Installing the precast footings
- Tight clearance with a large boulder which could not be removed
- Building the stream channel for within the bridge
- Unloading the first bridge section
- First bridge section is installed
- Connecting bridge sections together
- Positioning a precast section
- Swinging a curb wall into position
- Installing the curb walls of the bridge with an Ashlar Stone finish
- Bridge backfill and barrier membrane installed
- Backfilling the bridge structure
- Completing gravel installation on top of the bridge
- Removing existing substandard base materials
- Installing 1.5″ Crushed Gravel
- Installing 6″ minus gravel base on the bridge approaches
- Installing 6″ minus gravel base on the bridge approaches
- Installing Class C Stone to the extremely steep roadside slopes
- Looking west from the bridge
- Almost ready for asphalt pavement
- Final grading and rolling prior to paving
- The view downstream from the new bridge
- Looking through the new bridge toward the historic dam
- Landscape plantings with native plants and site boulders
- A view of the downstream side of the bridge upon completion
- The finished project
- The historic dam after construction was completed with no disturbance to the structure