Project completed October, 2007
Location: Freedom, NH
Owner: Town of Freedom, NH
Contracted By: Town of Freedom Highway Department
Project Description
Project Background
Project Goals
Solution: Trucks delivering the precast rigid frame bridge were required to back a little over 1 mile into the site. The trucks carry other materials to and from the site were required to back nearly a quarter mile.
Issue: Overhead utilities were in a location that limited crane access.
Solution: A larger crane was required to be able to reach under the overhead utilities.
- Excavation for one of the wing walls
- Excavating for footings, leaving the middle for channel simulation
- Excavating for footings
- Sediment Detention Ponds (old way of collecting sediment)
- Water Diversion